HVAC Testing, Adjusting & Balancing Projects |

| Owner/Client: | USAA |
| Project Size: | 500,000 sq ft. |
| Architect: | Elements |
| Building Automation Contractor: | Siemens Industry, Inc |
| Mech. Engineer: | Tilden, Lobnitz, Cooper |
| TAB Firm: | Southern Independent Testing Agency (SITA) |
| Construction Management: | ABI Construction Services |
This multi phase project included Mechanical renovations as well as HVAC controls upgrade to the Tampa Office. The Campus includes a seven-story main building, a child development center and several support structures. The building houses a 500+ seat cafeteria with a full-service kitchen, conference rooms, loading docks, drive-in claims area, fitness center, and storage areas.
SITA provided Testing, Adjusting, & Balancing (TAB) services for the 500,000 sq ft building, which included extensive TAB services related to the ventilation and chilled water systems to ensure a functional building SERO was awarded the LEED Gold certification — Existing Buildings from the U.S. Green Building Council, the first existing building in the state of Florida to receive this certification.

| Owner/Client: | City of Tampa |
| Project Size: | 66,000 sq ft. |
| Architect: | Stanley Saitowitz Mech. |
| Engineer: | Tilden, Lobnitz, Cooper |
| TAB Firm: | (SITA) |
| Construction Management: | Skanska USA Building, Inc. |
TMA constructed a new 66,000-square-foot facility in downtown Tampa. SITA provided HVAC Testing, Adjusting, & Balancing (TAB) services for the 66,000 sf building, which included extensive TAB services related to the ventilation and chilled water systems to ensure a functional building. The museum will become a nationally recognized major art destination and premier venue for residents and visitors. Five expansive interior galleries, one exterior sculpture gallery, and an educational classroom equipped with the latest technology offer visitors a wide variety of visual art experiences.
| Owner/Client: | Syniverse Corporation |
| Project Size: | 200,000 sq ft. |
| Architect: | Collman & Karsky Architects Mech. |
| Engineer: | Smith, Seikman & Reed, Inc. |
| TAB Firm: | (SITA) |
| Construction Management: | RENOVATION CONSTRUCTION: Relocation of Corporate Facility |
SITA provided HVAC Testing, Adjusting, & Balancing (TAB) services for the 200,000 sf building, which included extensive TAB services related to the ventilation and chilled water systems to ensure a functional building. The project included converting10,000 sf on the first floor of the existing office building to a 6,000 sf network operations center as well as designing 2,000 sf of research and technology laboratories. Special features include raised access floors, Liebert air handling units, gas fire suppression systems, and a variety of sophisticated security and control systems.
| Owner/Client: | University of Central Florida |
| Project Size: | 75,000 sq. ft. |
| Project Cost: | $12.4 Million |
| Architect: | Farmer Baker Barrios |
| Engineer: | Tilden, Lobnitz, Cooper |
| TAB Firm: | (SITA) |
| Construction Management: | PPI Construction |
The new Psychology Building includes classrooms, research laboratories, a clinic, faculty and undergraduate offices and an auditorium. SITA provided HVAC Testing, Adjusting, & Balancing (TAB) services for the 75,000 sf building, which included extensive TAB services related to the ventilation and chilled water systems to ensure a functional building.
| Owner/Client: | Progressive Insurance |
| Project Size: | 150,000 sq. ft. |
| Project Cost: | $26.5 Million |
| Architect: | HGF Architects |
| Engineer: | Bacils Karpinski & Associates |
| TAB Firm: | (SITA) |
| Construction Management: | Beck Group |
This fast-track 150,000 sf call center for Progressive, consisted of a 3-story Call Center that seats 1000 employees and a 2-story amenities building. The project also included infrastructure tie-ins to their existing campus for communications, and a stand-alone energy plant. The custom Air Enterprises (70,000 cfm) roof top units, with multiple fans, required extensive coordination with the controls contractor and mechanical contractor to ensure proper operation.

| Owner/Client: | H. Lee Moffitt Cancer Center |
| Project Size: | 425,000 sq. ft. |
| Architect: | NBBJ/Hunton Brandy Architects |
| Engineer: | GRG Consulting Engineers |
| TAB Firm: | (SITA) |
The expansion of the existing 400,000 sf complex consisted of a 175,000 sf clinic addition to the existing facility, and a separate 250,000 sf Research Laboratory Building connected by tunnel and bridge to the Clinic. SITA provided HVAC Testing, Adjusting, & Balancing (TAB) services for the 425,000 sf building, which included extensive TAB services related to the ventilation and chilled water systems to ensure a functional building.
| Owner/Client: | City of Dunedin |
| Project Size: | 60,000 sq. ft. |
| Architect: | Collman, Karsky & Associates |
| Engineer: | Tilden, Lobnitz, Cooper |
| TAB Firm: | (SITA) |
| Construction Management: | Creative Contractors |
Designed for theater and dance productions, banquets, indoor sports, dance, weight training, and exercise classes, the new center will provide flexible spaces for classrooms, crafts, games, preschool, a branch library, and administrative offices for the Dunedin Leisure Services Department. Ample exterior green spaces will accommodate athletic and recreational activities, existing courts and fields, a fully accessible playground, music festivals and art harvest fairs. SITA provided HVAC Testing, Adjusting, & Balancing (TAB) services for the 60,000 sf building, which is registered for basic LEED certification.